PK0-005 · Question #460
PK0-005 Question #460: Real Exam Question with Answer & Explanation
The correct answer is A: The team needs to adjust the planned work based on results.. The chart shows frequent mismatches between committed work and actual work completed, with the team sometimes underdelivering and other times overdelivering. This inconsistency suggests that the team needs to adjust its planning based on actual performance to improve estimation
Question
Given the following chart showing committed work (orange) vs. actual work completed (blue) across 10 sprints: Which of the following best describes the team's performance?
Options
- AThe team needs to adjust the planned work based on results.
- BThe team's velocity is getting better.
- CThe team understands its velocity and is planning in an accurate manner.
- DThe team is doing more work than planned.
Explanation
The chart shows frequent mismatches between committed work and actual work completed, with the team sometimes underdelivering and other times overdelivering. This inconsistency suggests that the team needs to adjust its planning based on actual performance to improve estimation
Topics
Community Discussion
No community discussion yet for this question.