PK0-005 · Question #458
A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?
The correct answer is A. Scrum. Scrum is an Agile framework that is well-suited for projects with rapidly changing requirements. It operates in iterative cycles called sprints, allowing for regular reassessment and adaptation of project goals. This flexibility makes Scrum ideal for environments where the compan
Question
A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?
Options
- AScrum
- BExtreme programming
- CWaterfall
- DKanban
How the community answered
(40 responses)- A83% (33)
- B3% (1)
- C10% (4)
- D5% (2)
Explanation
Scrum is an Agile framework that is well-suited for projects with rapidly changing requirements. It operates in iterative cycles called sprints, allowing for regular reassessment and adaptation of project goals. This flexibility makes Scrum ideal for environments where the company's strategy and product requirements evolve frequently, as it facilitates continuous improvement and responsiveness to change.