PK0-005 · Question #457

Which of the following tasks should the project manager complete first when validating deliverables?

The correct answer is C. Review the project objectives. Validating deliverables involves ensuring that the project's outputs meet the defined requirements and objectives. The first step in this process is to review the project objectives to confirm that the deliverables align with the intended goals. This review provides a benchmark…

Project Management Concepts

Question

Which of the following tasks should the project manager complete first when validating deliverables?

Options

  • AAssess the documentation.
  • BObtain stakeholder feedback.
  • CReview the project objectives.
  • DMitigate risks.

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    92% (47)
  • D
    4% (2)

Explanation

Validating deliverables involves ensuring that the project's outputs meet the defined requirements and objectives. The first step in this process is to review the project objectives to confirm that the deliverables align with the intended goals. This review provides a benchmark against which the deliverables can be assessed, ensuring that they fulfill the project's purpose before seeking stakeholder feedback or assessing documentation.

Topics

#Deliverable Validation#Project Objectives#Project Process#Scope Management