nerdexam
CompTIA

PK0-005 · Question #273

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

The correct answer is D. Reinforce the rules of engagement. The rules of engagement are the guidelines and expectations that define the relationship between the contractor and the company. They may include topics such as communication, confidentiality, access, security, performance, and compliance. The project manager should reinforce…

Project Management Concepts

Question

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

Options

  • AEscalate to vendor management.
  • BConsult the request for proposal.
  • CReview the meeting cadence.
  • DReinforce the rules of engagement.

How the community answered

(34 responses)
  • A
    15% (5)
  • B
    3% (1)
  • C
    9% (3)
  • D
    74% (25)

Explanation

The rules of engagement are the guidelines and expectations that define the relationship between the contractor and the company. They may include topics such as communication, confidentiality, access, security, performance, and compliance. The project manager should reinforce the rules of engagement with the contractor to ensure that they understand and respect the boundaries and protocols of the company. This will help to avoid any potential conflicts, misunderstandings, or breaches of contract.

Topics

#Contractor management#Communication protocols#Rules of engagement#Stakeholder management

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice