A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and…

The correct answer is B. Review the requested change. The project manager should review the requested change first to assess its impact, feasibility, and alignment with the project objectives and scope. Reviewing the change will help the project manager to determine if the change is necessary, beneficial, and acceptable to the…

Project Management Concepts

Question

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

Options

  • AEscalate the change to the CCB.
  • BReview the requested change.
  • CDocument the change recommendations.
  • DValidate the implementation of the requested change.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    82% (23)
  • C
    11% (3)
  • D
    4% (1)

Explanation

The project manager should review the requested change first to assess its impact, feasibility, and alignment with the project objectives and scope. Reviewing the change will help the project manager to determine if the change is necessary, beneficial, and acceptable to the stakeholders. The project manager should also consider the risks, costs, and quality implications of the change before proceeding to the next steps of the change management process.

Topics

#Change Management Process#Change Request#Project Control#Client Management