PK0-005 · Question #272
A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save an
The correct answer is A. Application deployment. The scenario describes a planned, scheduled release of an application during off-hours (third Friday of the month), with advance user notification about downtime. This is the classic definition of an application deployment - pushing a new version of software to production. A main
Question
A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?
Options
- AApplication deployment
- BRollback plans
- CValidation checks
- DMaintenance window schedules
How the community answered
(30 responses)- A93% (28)
- B3% (1)
- C3% (1)
Explanation
The scenario describes a planned, scheduled release of an application during off-hours (third Friday of the month), with advance user notification about downtime. This is the classic definition of an application deployment - pushing a new version of software to production. A maintenance window (D) is the scheduled time slot used for this activity, but the action itself is a deployment. Rollback plans (B) are contingency plans in case deployment fails. Validation checks (C) verify functionality but are part of the deployment process, not the activity itself.
Topics
Community Discussion
No community discussion yet for this question.