nerdexam
CompTIACompTIA

PK0-005 · Question #271

PK0-005 Question #271: Real Exam Question with Answer & Explanation

The correct answer is A: 23. The number of items in the backlog can be determined by looking at the "Commitment" column for each sprint in the provided chart. For Sprint 5, there is a commitment of completing 23 items, which is the highest among all sprints. This indicates that there are at least 23 items in

Project Management Concepts

Question

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following: Which of the following most likely represents the number of items in the backlog?

Options

  • A23
  • B5
  • C10
  • D15

Explanation

The number of items in the backlog can be determined by looking at the "Commitment" column for each sprint in the provided chart. For Sprint 5, there is a commitment of completing 23 items, which is the highest among all sprints. This indicates that there are at least 23 items in the backlog to be worked on. This is consistent with the concept of agile project management, which allows for changes and additions to the project scope based on customer feedback and changing

Topics

#Backlog Management#Agile Metrics#Team Performance Monitoring#Committed vs. Completed

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions