PK0-005 · Question #270

After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?

The correct answer is A. Rollback plan. A rollback plan is a part of the project management plan that defines how to revert the system to its previous state or baseline if the change or migration fails or causes unacceptable impacts. A rollback plan is different from a contingency plan, which is a plan to deal with a s

Project Management Concepts

Question

After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?

Options

  • ARollback plan
  • BRelease plan
  • CDeployment plan
  • DContingency plan

How the community answered

(36 responses)
  • A
    92% (33)
  • B
    3% (1)
  • D
    6% (2)

Explanation

A rollback plan is a part of the project management plan that defines how to revert the system to its previous state or baseline if the change or migration fails or causes unacceptable impacts. A rollback plan is different from a contingency plan, which is a plan to deal with a specific risk event that may or may not occur. A release plan and a deployment plan are not relevant to the scenario, as they are used to plan and execute the delivery and installation of the system, not to

Topics

#Rollback plan#Deployment failure#System recovery#Post-migration