PK0-005 · Question #270
After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?
The correct answer is A. Rollback plan. A rollback plan is a part of the project management plan that defines how to revert the system to its previous state or baseline if the change or migration fails or causes unacceptable impacts. A rollback plan is different from a contingency plan, which is a plan to deal with a s
Question
After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?
Options
- ARollback plan
- BRelease plan
- CDeployment plan
- DContingency plan
How the community answered
(36 responses)- A92% (33)
- B3% (1)
- D6% (2)
Explanation
A rollback plan is a part of the project management plan that defines how to revert the system to its previous state or baseline if the change or migration fails or causes unacceptable impacts. A rollback plan is different from a contingency plan, which is a plan to deal with a specific risk event that may or may not occur. A release plan and a deployment plan are not relevant to the scenario, as they are used to plan and execute the delivery and installation of the system, not to
Topics
Community Discussion
No community discussion yet for this question.