The correct answer is B: Mitigate. Mitigate is a risk strategy that involves taking actions to reduce the probability or impact of a risk. By applying new updates to a program in a sandbox environment, the software engineer is testing the changes before implementing them in the actual system, thus minimizing the c

Project Management Concepts

Question

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

Options

  • ATransfer
  • BMitigate
  • CAvoid
  • DAccept

Explanation

Mitigate is a risk strategy that involves taking actions to reduce the probability or impact of a risk. By applying new updates to a program in a sandbox environment, the software engineer is testing the changes before implementing them in the actual system, thus minimizing the chance of errors or failures that could affect the project.

Topics

#Risk mitigation#Risk strategies#Sandbox environment#IT operations

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions