PK0-005 · Question #258
PK0-005 Question #258: Real Exam Question with Answer & Explanation
The correct answer is C: Project schedule. A project schedule is an artifact that shows the sequence, duration, and dependencies of the project activities, as well as the resources assigned to each activity. A project schedule helps the project team understand what needs to be done, who needs to complete the tasks, and wh
Question
A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?
Options
- ASWOT
- BRisk register
- CProject schedule
- DRAC
Explanation
A project schedule is an artifact that shows the sequence, duration, and dependencies of the project activities, as well as the resources assigned to each activity. A project schedule helps the project team understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. A project schedule can also help monitor and control the project progress and performance.
Topics
Community Discussion
No community discussion yet for this question.