nerdexam
CompTIACompTIA

PK0-005 · Question #258

PK0-005 Question #258: Real Exam Question with Answer & Explanation

The correct answer is C: Project schedule. A project schedule is an artifact that shows the sequence, duration, and dependencies of the project activities, as well as the resources assigned to each activity. A project schedule helps the project team understand what needs to be done, who needs to complete the tasks, and wh

Tools and documentation

Question

A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?

Options

  • ASWOT
  • BRisk register
  • CProject schedule
  • DRAC

Explanation

A project schedule is an artifact that shows the sequence, duration, and dependencies of the project activities, as well as the resources assigned to each activity. A project schedule helps the project team understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. A project schedule can also help monitor and control the project progress and performance.

Topics

#Project scheduling#Project artifacts#Task management#Project planning

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions