PK0-005 · Question #258
A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this…
The correct answer is C. Project schedule. A project schedule captures the three key elements asked about: the tasks (what needs to be done), the assigned resources (who completes the tasks), and the timelines (when tasks must be completed). A SWOT analyzes strengths, weaknesses, opportunities, and threats. A risk…
Question
A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?
Options
- ASWOT
- BRisk register
- CProject schedule
- DRAC
How the community answered
(44 responses)- A5% (2)
- B5% (2)
- C77% (34)
- D14% (6)
Explanation
A project schedule captures the three key elements asked about: the tasks (what needs to be done), the assigned resources (who completes the tasks), and the timelines (when tasks must be completed). A SWOT analyzes strengths, weaknesses, opportunities, and threats. A risk register tracks identified risks and responses. A RACI (not RAC) defines roles and responsibilities but does not include task timelines or scheduling details.