PK0-005 · Question #259
PK0-005 Question #259: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-005 to reveal the answer and full explanation for question #259. The question stem and answer options stay visible for context.
Question
A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
Options
- A9 days and $3,000
- B10 days and $3,200
- C12 days and $3,800
- D14 days and $4,000
Unlock PK0-005 to see the answer
You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.