nerdexam
CompTIACompTIA

PK0-005 · Question #256

PK0-005 Question #256: Real Exam Question with Answer & Explanation

The correct answer is A: Rollback plans. A rollback plan is a contingency plan that describes how to revert the system to its previous state in case the change fails or causes problems. A rollback plan is important to minimize the impact of a failed change and ensure the system's availability and functionality. A deploy

Tools and documentation

Question

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

Options

  • ARollback plans
  • BProject management plan
  • CDeployment plan
  • DAsset management plan
  • ECommunication plan
  • FResource management plan

Explanation

A rollback plan is a contingency plan that describes how to revert the system to its previous state in case the change fails or causes problems. A rollback plan is important to minimize the impact of a failed change and ensure the system's availability and functionality. A deployment plan is a document that outlines the steps and procedures for implementing the change in the production environment. A deployment plan is important to ensure the change is executed smoothly, efficiently, and securely, and that the system meets the expected performance and quality

Topics

#Change Management#Deployment Planning#Rollback Procedures#IT Operations

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions