PK0-005 · Question #256
PK0-005 Question #256: Real Exam Question with Answer & Explanation
The correct answer is A: Rollback plans. A rollback plan is a contingency plan that describes how to revert the system to its previous state in case the change fails or causes problems. A rollback plan is important to minimize the impact of a failed change and ensure the system's availability and functionality. A deploy
Question
An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).
Options
- ARollback plans
- BProject management plan
- CDeployment plan
- DAsset management plan
- ECommunication plan
- FResource management plan
Explanation
A rollback plan is a contingency plan that describes how to revert the system to its previous state in case the change fails or causes problems. A rollback plan is important to minimize the impact of a failed change and ensure the system's availability and functionality. A deployment plan is a document that outlines the steps and procedures for implementing the change in the production environment. A deployment plan is important to ensure the change is executed smoothly, efficiently, and securely, and that the system meets the expected performance and quality