Project Life Cycle Phases

Question

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

Options

  • ABringing attention to the project sponsor
  • BSharing lessons learned
  • CCollecting feedback
  • DCelebrating the team's hard work