During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should…

The correct answer is D. Schedule a call with the vendor PM and vendor executive to review the statement of work. The statement of work (SOW) is the contractual document that defines the agreed-upon deliverables, acceptance criteria, and payment milestones. When UAT fails, it means the vendor has not met the conditions defined in the SOW for this phase - and payment is typically contingent…

Project Life Cycle Phases

Question

During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?

Options

  • AEscalate the issue with the project sponsor and ask for assistance in managing the situation.
  • BWork with the vendor to achieve a compromise that benefits everyone.
  • CApprove the invoice to avoid damaging the relationship with the vendor.
  • DSchedule a call with the vendor PM and vendor executive to review the statement of work.

How the community answered

(39 responses)
  • A
    10% (4)
  • B
    18% (7)
  • C
    5% (2)
  • D
    67% (26)

Explanation

The statement of work (SOW) is the contractual document that defines the agreed-upon deliverables, acceptance criteria, and payment milestones. When UAT fails, it means the vendor has not met the conditions defined in the SOW for this phase - and payment is typically contingent on accepted deliverables. The program manager should schedule a call with both the vendor PM and vendor executive to formally review the SOW, clarify what was agreed upon, and demonstrate why the invoice cannot be approved as-is. Option A (escalating to sponsor) may be appropriate if the situation escalates, but the first step is to address it directly using the contract. Option B (compromise) may undermine contractual rights. Option C (approving the invoice) rewards non-performance and is inappropriate.

Topics

#Contract Management#Vendor Management#Acceptance Testing#Problem Resolution