nerdexam
CompTIA

PK0-005 · Question #253

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identif

The correct answer is D. Traceability matrix. A Requirements Traceability Matrix (RTM) links each requirement or feature back to its origin - including the stakeholder or business need that requested it - and traces it forward through design, development, and testing. This makes it the correct document to identify who reques

Tools and documentation

Question

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

Options

  • AIssue log
  • BRisk register
  • CDefect log
  • DTraceability matrix

How the community answered

(56 responses)
  • A
    4% (2)
  • B
    5% (3)
  • C
    9% (5)
  • D
    82% (46)

Explanation

A Requirements Traceability Matrix (RTM) links each requirement or feature back to its origin - including the stakeholder or business need that requested it - and traces it forward through design, development, and testing. This makes it the correct document to identify who requested a specific item that is causing a regression failure. The issue log (A) records problems encountered but does not map items to their requestors. The risk register (B) tracks identified risks. The defect log (C) records bugs found during testing but does not trace requirements back to their source. The RTM is the authoritative document for requirement origin and coverage.

Topics

#Traceability matrix#Project documentation#Requirements management#Project monitoring and control

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice