PK0-005 · Question #240
PK0-005 Question #240: Real Exam Question with Answer & Explanation
The correct answer is B: To obtain project sign-off. A project closure meeting is a formal gathering held at the end of a project timeline. Its chief purpose is to evaluate the project's performance, identify and discuss the achieved outcomes, successes, and challenges, and confirm that all predefined tasks and objectives have been
Question
A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?
Options
- ATo move the system to a production environment
- BTo obtain project sign-off
- CTo formalize the end of the contract
- DTo release resources
Explanation
A project closure meeting is a formal gathering held at the end of a project timeline. Its chief purpose is to evaluate the project's performance, identify and discuss the achieved outcomes, successes, and challenges, and confirm that all predefined tasks and objectives have been completed successfully. The project closure meeting also involves obtaining project sign-off from all necessary parties, such as the project sponsor, the client, the stakeholders, and the team members. Project sign-off is the official approval that the project has met the agreed-upon criteria and quality standards, and that the project is formally closed.