nerdexam
CompTIA

PK0-005 · Question #239

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone

The correct answer is C. assessing the resource pool.. Assessing the resource pool means evaluating the available people, their qualifications, roles, costs, and capacity before committing them to the project. Reviewing SOW, grading resumes, evaluating titles and salaries, and estimating hours per FTE are all analytical activities ai

Project Management Concepts

Question

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

Options

  • Anegotiating resources.
  • Bassigning resources.
  • Cassessing the resource pool.
  • Dadding resources to the schedule.

How the community answered

(53 responses)
  • A
    13% (7)
  • B
    4% (2)
  • C
    77% (41)
  • D
    6% (3)

Explanation

Assessing the resource pool means evaluating the available people, their qualifications, roles, costs, and capacity before committing them to the project. Reviewing SOW, grading resumes, evaluating titles and salaries, and estimating hours per FTE are all analytical activities aimed at understanding what resources are available and suitable - not yet assigning or negotiating. Assigning resources comes after the assessment; negotiating involves discussion with resource owners; adding to the schedule is a later scheduling step.

Topics

#Resource Management#Project Planning#Resource Assessment#FTE Evaluation

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice