PK0-005 · Question #241
During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?
The correct answer is A. Issue log. An issue log is the correct first tool because the constraints being identified during quality analysis are current, active problems requiring tracking and prioritization for resolution. A defect log tracks product defects specifically. A risk register tracks potential future…
Question
During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?
Options
- AIssue log
- BDefect log
- CRisk register
- DChange log
How the community answered
(34 responses)- A79% (27)
- B12% (4)
- C6% (2)
- D3% (1)
Explanation
An issue log is the correct first tool because the constraints being identified during quality analysis are current, active problems requiring tracking and prioritization for resolution. A defect log tracks product defects specifically. A risk register tracks potential future events, not current problems. A change log records approved scope changes. The issue log's purpose - capturing, assigning ownership, and prioritizing resolution of active issues - directly matches what the project manager needs in this scenario.