PK0-005 · Question #130
PK0-005 Question #130: Real Exam Question with Answer & Explanation
The correct answer is C: Scrum. Scrum is an agile framework designed for delivering incremental value within fixed-length iterations called sprints, making it suitable for projects expecting value in timeboxed periods.
Project Management Concepts
Question
Which of the following methodologies/frameworks should be used when incremental value is expected in a timeboxed period?
Options
- APRINCE2
- BWaterfall
- CScrum
- DSLDC
Explanation
Scrum is an agile framework designed for delivering incremental value within fixed-length iterations called sprints, making it suitable for projects expecting value in timeboxed periods.
Common mistakes.
- A. PRINCE2 (PRojects IN Controlled Environments) is a structured project management method focusing on clear roles, responsibilities, and control, but it doesn't inherently mandate incremental value delivery in timeboxed periods in the same way Scrum does.
- B. Waterfall is a linear, sequential project management approach where each phase must be completed before the next begins, which is contrary to incremental value delivery in timeboxed periods.
- D. SLDC (Software Development Life Cycle) is a general term for the process of developing software, not a specific methodology that inherently focuses on incremental, timeboxed value delivery like Scrum.
Concept tested. Agile methodologies - Scrum framework
Topics
#Scrum#Agile methodologies#Timeboxing#Incremental delivery