PK0-005 · Question #131
PK0-005 Question #131: Real Exam Question with Answer & Explanation
The correct answer is B: Prepare new knowledge base documentation.. If users are not adopting a new self-service system and are instead contacting HR for help, the project manager should have ensured comprehensive knowledge base documentation was prepared as part of the execution plan.
Question
A project manager has just finished overseeing the implementation of a new, self-service benefits enrollment system. Many employees, however, are calling the human resources team for assistance instead of using the self-service system. Which of the following should the project manager have done as part of the execution plan?
Options
- AEstablish a minimally viable product.
- BPrepare new knowledge base documentation.
- CUpdate the project baseline and schedule.
- DPeriodically review vendor performance.
Explanation
If users are not adopting a new self-service system and are instead contacting HR for help, the project manager should have ensured comprehensive knowledge base documentation was prepared as part of the execution plan.
Common mistakes.
- A. Establishing a minimally viable product (MVP) is typically part of the planning or initial development phase to deliver core functionality early, not a solution for post-implementation user adoption issues.
- C. Updating the project baseline and schedule is part of change control if the project scope or timeline changes, not a direct action to address user training or support needs post-implementation.
- D. Periodically reviewing vendor performance is important for vendor management, but it doesn't directly address the user adoption challenge related to a lack of self-help resources for the new system.
Concept tested. Project execution - user training and support documentation
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/project-execution-process