nerdexam
CompTIA

PK0-005 · Question #125

A project has been initiated to provide insurance forms for a company. A constraint for this project is that the insurance commission in each state where the company underwrites has to approve each…

The correct answer is A. Regulatory impacts. The requirement for insurance commission approval in each state represents a regulatory impact on the project, as it involves adherence to external legal standards.

Project Management Concepts

Question

A project has been initiated to provide insurance forms for a company. A constraint for this project is that the insurance commission in each state where the company underwrites has to approve each form. Which of the following compliance considerations BEST describes this scenario?

Options

  • ARegulatory impacts
  • BEnvironmental impacts
  • COrganizational impacts
  • DSensitive data types

How the community answered

(54 responses)
  • A
    87% (47)
  • B
    7% (4)
  • C
    2% (1)
  • D
    4% (2)

Why each option

The requirement for insurance commission approval in each state represents a regulatory impact on the project, as it involves adherence to external legal standards.

ARegulatory impactsCorrect

Regulatory impacts refer to the effects of laws, regulations, and industry standards imposed by government bodies or oversight agencies on a project's execution and deliverables, such as state insurance commissions dictating form approval. These external rules are mandatory constraints that must be adhered to for the project to be successful and legally compliant.

BEnvironmental impacts

Environmental impacts relate to the project's effect on the natural environment, which is not described here.

COrganizational impacts

Organizational impacts refer to changes within the company itself due to the project, not external approval bodies.

DSensitive data types

While insurance forms might contain sensitive data, the constraint itself is about the approval process by an external body, not the data type directly.

Concept tested: Project constraints - regulatory compliance

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/project-constraints

Topics

#Regulatory compliance#Project constraints#External factors

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice