PK0-005 · Question #124

PK0-005 Question #124: Real Exam Question with Answer & Explanation

The correct answer is B: Preliminary scope statement. After defining project objectives and success criteria, the next crucial element to define in a project charter is the preliminary scope statement.

Tools and documentation

Question

A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?

Options

  • AProposed solution design
  • BPreliminary scope statement
  • CResponsibility assignment matrix
  • DInitial budget baseline

Explanation

After defining project objectives and success criteria, the next crucial element to define in a project charter is the preliminary scope statement.

Common mistakes.

  • A. A proposed solution design is part of detailed planning and solution development, not typically included in the high-level project charter.
  • C. A responsibility assignment matrix (RAM) is a detailed planning output used to define roles and responsibilities, which comes much later than the charter.
  • D. While an initial budget is part of the charter, the 'initial budget baseline' implies a more refined and approved budget, often developed after the preliminary scope is established.

Concept tested. Project charter components - preliminary scope

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/project-charter

Topics

#Project Charter#Preliminary Scope Statement#Project Initiation#Project Documentation