The correct answer is B: Preliminary scope statement. After defining project objectives and success criteria, the next crucial element to define in a project charter is the preliminary scope statement.
Question
A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?
Options
- AProposed solution design
- BPreliminary scope statement
- CResponsibility assignment matrix
- DInitial budget baseline
Explanation
After defining project objectives and success criteria, the next crucial element to define in a project charter is the preliminary scope statement.
Common mistakes.
- A. A proposed solution design is part of detailed planning and solution development, not typically included in the high-level project charter.
- C. A responsibility assignment matrix (RAM) is a detailed planning output used to define roles and responsibilities, which comes much later than the charter.
- D. While an initial budget is part of the charter, the 'initial budget baseline' implies a more refined and approved budget, often developed after the preliminary scope is established.
Concept tested. Project charter components - preliminary scope
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/project-charter