nerdexam
CompTIA

PK0-005 · Question #123

Which of the following would be the MOST beneficial to determine whether a project has met the defined objectives?

The correct answer is D. Key performance indicators. To determine whether a project has met its defined objectives, Key Performance Indicators (KPIs) are the most beneficial. KPIs are quantifiable metrics specifically chosen to measure progress towards achieving strategic goals and outcomes.

Project Management Concepts

Question

Which of the following would be the MOST beneficial to determine whether a project has met the defined objectives?

Options

  • ASchedule variance
  • BCost variance
  • CWork breakdown structure
  • DKey performance indicators

How the community answered

(54 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    2% (1)
  • D
    91% (49)

Why each option

To determine whether a project has met its defined objectives, Key Performance Indicators (KPIs) are the most beneficial. KPIs are quantifiable metrics specifically chosen to measure progress towards achieving strategic goals and outcomes.

ASchedule variance

Schedule variance measures whether the project is ahead or behind schedule, which is important for project management but doesn't directly assess if the core objectives were met.

BCost variance

Cost variance measures whether the project is over or under budget, which is important for financial health but doesn't directly assess objective achievement.

CWork breakdown structure

A Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team; it defines the work, not measures objective attainment.

DKey performance indicatorsCorrect

Key Performance Indicators (KPIs) are quantifiable measures used to evaluate the success of an organization or project in meeting its objectives. By defining and tracking specific KPIs, a project manager can directly assess whether the project has achieved its intended goals and delivered the expected value.

Concept tested: Project success measurement (KPIs)

Topics

#Project objectives#Project success measurement#Key performance indicators#Project evaluation

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice