PK0-005 · Question #115
During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT?
The correct answer is B. Work with the business analyst to document the new epic. In an agile context, when new scope is identified by the product owner during a demonstration, the Scrum Master should facilitate its proper documentation for inclusion in the backlog. This involves working with relevant team members to define the new work item.
Question
During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT?
Options
- ACreate a change request for the change advisory board.
- BWork with the business analyst to document the new epic.
- CReject the change to prevent scope creep.
- DUpdate the risk register and the work in the mitigation plan.
How the community answered
(24 responses)- A8% (2)
- B88% (21)
- C4% (1)
Why each option
In an agile context, when new scope is identified by the product owner during a demonstration, the Scrum Master should facilitate its proper documentation for inclusion in the backlog. This involves working with relevant team members to define the new work item.
Agile methodologies typically do not use a formal 'change request for the change advisory board' in the same way as traditional waterfall projects for backlog additions.
When new scope is identified by the product owner in an agile environment, the Scrum Master's role is to facilitate the process of capturing and documenting this new requirement. Working with a business analyst (or product owner if BA is not present) to define the new epic or user story ensures it is clearly understood and ready for refinement and prioritization in the product backlog.
The Scrum Master should not reject new scope from the product owner; instead, they should facilitate its proper capture and addition to the backlog for prioritization by the product owner.
Updating the risk register and mitigation plan might be a subsequent step if the new epic introduces significant risks, but the immediate next step is to document the new scope itself.
Concept tested: Agile Scrum backlog management
Source: https://www.scrum.org/resources/what-is-scrum