Project A and Project B share a team member. The team member is falling behind on a task for Project B. Which of the following is the BEST action to take to get the task for Project B back on track?

The correct answer is A. Negotiate to get more of the team member's available time. When a team member shared between projects falls behind, the best course of action is to address the resource allocation directly. Negotiating for more of their time for the struggling project helps resolve the underlying resource contention.

Project Management Concepts

Question

Project A and Project B share a team member. The team member is falling behind on a task for Project B. Which of the following is the BEST action to take to get the task for Project B back on track?

Options

  • ANegotiate to get more of the team member's available time.
  • BAssign the team member to work overtime to finish the task.
  • CSpeed up completion of the task by assisting the team member.
  • DHave the project manager complete the task.

How the community answered

(30 responses)
  • A
    77% (23)
  • B
    13% (4)
  • C
    7% (2)
  • D
    3% (1)

Why each option

When a team member shared between projects falls behind, the best course of action is to address the resource allocation directly. Negotiating for more of their time for the struggling project helps resolve the underlying resource contention.

ANegotiate to get more of the team member's available time.Correct

Negotiating for more of the team member's available time addresses the fundamental issue of resource contention and allocation, especially when a resource is shared across multiple projects. This involves discussion with the other project manager or functional manager to adjust priorities or allocate additional time to Project B, which is often the most effective long-term solution.

BAssign the team member to work overtime to finish the task.

Assigning overtime is a short-term fix that can lead to burnout, decreased quality, and increased costs, and doesn't solve the underlying resource conflict.

CSpeed up completion of the task by assisting the team member.

Assisting the team member might provide temporary relief but doesn't resolve the resource constraint and may not be scalable or sustainable for the project manager.

DHave the project manager complete the task.

The project manager completing the task is generally not an appropriate or sustainable solution, as it diverts the PM from their core responsibilities and doesn't empower the team member.

Concept tested: Resource allocation and conflict resolution

Topics

#Resource management#Resource allocation#Task management