CompTIA
PK0-005 · Question #114
A project plan included budgeted funding to set up only a specified number of workstations. A department manager asked a project manager to set up additional workstations just in case the workstations
Sign in or unlock PK0-005 to reveal the answer and full explanation for question #114. The question stem and answer options stay visible for context.
Project Management Concepts
Question
A project plan included budgeted funding to set up only a specified number of workstations. A department manager asked a project manager to set up additional workstations just in case the workstations are needed in the future. Which of the following should the project manager do?
Options
- AAsk the sponsor for additional funding to accommodate the request.
- BEscalate the request to the senior management team.
- CAdvise that a change request would need to be approved.
- DInstruct the project team to set up the additional workstations.
Unlock PK0-005 to see the answer
You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Project change control#Scope management#Budget management#Stakeholder requests