PK0-004 · Question #999
Which of the following are key elements of the planning phase?
The correct answer is B. Procurement plan, change management plan, change control, budget. The planning phase produces detailed management plans across all knowledge areas. A procurement plan, change management plan, change control process, and budget are all developed during planning. Option A is mostly correct but incomplete as a full set. Option C includes…
Question
Which of the following are key elements of the planning phase?
Options
- ASchedule, communication plan requirements, risk management plan
- BProcurement plan, change management plan, change control, budget
- CCommunication plan change management plan, high-level risk, business case
- DLessons learned, project charter, project management plan, work breakdown structure
How the community answered
(41 responses)- A2% (1)
- B90% (37)
- C2% (1)
- D5% (2)
Explanation
The planning phase produces detailed management plans across all knowledge areas. A procurement plan, change management plan, change control process, and budget are all developed during planning. Option A is mostly correct but incomplete as a full set. Option C includes 'business case' and 'high-level risk,' which belong to the initiating phase. Option D includes 'lessons learned' (a closing phase output) and 'project charter' (an initiating phase document), making it incorrect. B is the most consistent set of pure planning-phase deliverables.
Topics
Community Discussion
No community discussion yet for this question.