PK0-004 · Question #995
A client asks the project manager to identify the critical path to complete a project. Which of the following activities does the project manager need to perform?
The correct answer is C. Analyze the project schedule and determine the sequence of tasks with the longest duration. The critical path is defined as the longest sequence of dependent (sequential) tasks through the project network that determines the earliest possible project completion date. Any delay to a task on the critical path directly delays the project. Option A describes resource…
Question
A client asks the project manager to identify the critical path to complete a project. Which of the following activities does the project manager need to perform?
Options
- APrioritize the tasks allocate the resources, and set the baseline
- BEvaluate the project schedule and identify the subtasks that have the shortest duration
- CAnalyze the project schedule and determine the sequence of tasks with the longest duration
- DIllustrate the tasks that lead up to the milestone with the most recent baseline
How the community answered
(64 responses)- A5% (3)
- B8% (5)
- C75% (48)
- D13% (8)
Explanation
The critical path is defined as the longest sequence of dependent (sequential) tasks through the project network that determines the earliest possible project completion date. Any delay to a task on the critical path directly delays the project. Option A describes resource planning and baselining, not critical path analysis. Option B is wrong because the critical path involves the longest, not shortest, duration path. Option D describes milestone-based reporting, not critical path methodology.