nerdexam
CompTIA

PK0-004 · Question #994

A major project milestone has been achieved. At a minimum, which of the following people should be notified?

The correct answer is C. Sponsor. The sponsor is the primary stakeholder who authorizes, funds, and champions the project. Major milestones represent significant progress toward the project's objectives, and the sponsor must be kept informed as the person ultimately accountable for the project's success…

Project management concepts

Question

A major project milestone has been achieved. At a minimum, which of the following people should be notified?

Options

  • AVendors
  • BCompany newsletter staff
  • CSponsor
  • DFellow project managers

How the community answered

(52 responses)
  • A
    2% (1)
  • B
    8% (4)
  • C
    87% (45)
  • D
    4% (2)

Explanation

The sponsor is the primary stakeholder who authorizes, funds, and champions the project. Major milestones represent significant progress toward the project's objectives, and the sponsor must be kept informed as the person ultimately accountable for the project's success. Vendors (A), newsletter staff (B), and fellow project managers (D) are secondary or optional audiences. At minimum, milestone communications flow upward to the sponsor before expanding to other audiences.

Topics

#milestone communication#sponsor notification#stakeholder management#communication plan

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice