PK0-004 · Question #972
PK0-004 Question #972: Real Exam Question with Answer & Explanation
The correct answer is B: Obtain formal approval. Even when a sponsor verbally declares the project a success, the project manager must obtain formal, documented approval before moving forward. A verbal statement at an interim review is not sufficient to close the project. Formal approval - typically a signed acceptance document
Question
Options
- AUpdate the project schedule.
- BObtain formal approval
- CBegin project closure.
- DRelease the project team to other projects.
Explanation
Even when a sponsor verbally declares the project a success, the project manager must obtain formal, documented approval before moving forward. A verbal statement at an interim review is not sufficient to close the project. Formal approval - typically a signed acceptance document - provides official authorization and creates an audit trail. Only after formal approval is secured should the project manager begin closure activities (C) or release the team (D). Updating the project schedule (A) is not relevant at this stage since the project is being accepted.
Community Discussion
No community discussion yet for this question.