A hurricane has caused millions of dollars'worth of damage, and volunteers are arriving in response. Which of the following activities would help to sequence the volunteers' repair activities?
The correct answer is C. Create a statement of work. A Statement of Work (SOW) documents all the specific work tasks and activities that need to be performed. Before you can sequence repair activities, you must first define and document what work needs to be done - that is the purpose of the SOW. It establishes the scope of work…
Question
A hurricane has caused millions of dollars'worth of damage, and volunteers are arriving in response. Which of the following activities would help to sequence the volunteers' repair activities?
Options
- ACreate an issue log.
- BIdentify work dependencies.
- CCreate a statement of work.
- DIdentify the project team.
How the community answered
(63 responses)- A6% (4)
- B3% (2)
- C73% (46)
- D17% (11)
Explanation
A Statement of Work (SOW) documents all the specific work tasks and activities that need to be performed. Before you can sequence repair activities, you must first define and document what work needs to be done - that is the purpose of the SOW. It establishes the scope of work in an organized fashion, providing the foundation from which activities can then be ordered and prioritized. An issue log (A) tracks problems, a project team identification (D) addresses staffing, and while identifying work dependencies (B) is part of sequencing, you need the SOW first to know what activities and dependencies exist.