PK0-004 · Question #961
PK0-004 Question #961: Real Exam Question with Answer & Explanation
The correct answer is A: Acceptance criteria. According to the PMBOK Guide, a complete project scope statement includes: product scope description, product acceptance criteria, project deliverables, project exclusions, project constraints, and project assumptions. The given list includes scope description, exclusions, assump
Question
Options
- AAcceptance criteria
- BDetailed team assignments
- CRisk register
- DProject schedule
Explanation
According to the PMBOK Guide, a complete project scope statement includes: product scope description, product acceptance criteria, project deliverables, project exclusions, project constraints, and project assumptions. The given list includes scope description, exclusions, assumptions, deliverables, and constraints - but is missing acceptance criteria (A). Acceptance criteria define the conditions that must be met for deliverables to be formally accepted by the customer or sponsor. Without them, there is no objective standard for sign-off or completion. Option B (team assignments) belongs in the resource management plan, not the scope statement. Option C (risk register) is a separate risk management artifact. Option D (project schedule) is produced during planning and is a separate document. Acceptance criteria is the only standard scope statement component missing from the list provided.
Community Discussion
No community discussion yet for this question.