PK0-004 · Question #952
A project manager asks a project coordinator to put together a milestone report to present to the board of directors showing how the project has progressed in the last three months. The coordinator…
The correct answer is A. The document is too lengthy and includes extraneous details. A document with 45 pages is too lengthy a one to keep an eye on each and every detail and
Tools and documentation
Question
A project manager asks a project coordinator to put together a milestone report to present to the board of directors showing how the project has progressed in the last three months. The coordinator shares a 45-page document detailing all that has happened so far on the project. Which of the following is MOST likely the issue?
Options
- AThe document is too lengthy and includes extraneous details
- BThe document follows the appropriate template for a communication plan
- CThe document contains data that is aggregated for an executive review.
- DThe documents clear regarding the objectives and status, including graphs.
How the community answered
(21 responses)- A90% (19)
- B5% (1)
- C5% (1)
Explanation
A document with 45 pages is too lengthy a one to keep an eye on each and every detail and
Topics
#milestone report#communication plan#executive reporting#stakeholder communication