A severe adverse event was not documented and has impacted the project. Which of the following will be MOST affected?

The correct answer is D. Project schedule. Planning and executing depends upon the documentation of its events. A mishap in such case may adversely affect the budget and time schedule of completing the project.

Project management concepts

Question

A severe adverse event was not documented and has impacted the project. Which of the following will be MOST affected?

Options

  • ACommunication plan
  • BProject charter
  • CAction item
  • DProject schedule

How the community answered

(23 responses)
  • A
    17% (4)
  • B
    9% (2)
  • C
    4% (1)
  • D
    70% (16)

Explanation

Planning and executing depends upon the documentation of its events. A mishap in such case may adversely affect the budget and time schedule of completing the project.

Topics

#risk management#issue documentation#project schedule#adverse event

Community Discussion

No community discussion yet for this question.