A severe adverse event was not documented and has impacted the project. Which of the following will be MOST affected?
The correct answer is D. Project schedule. Planning and executing depends upon the documentation of its events. A mishap in such case may adversely affect the budget and time schedule of completing the project.
Project management concepts
Question
A severe adverse event was not documented and has impacted the project. Which of the following will be MOST affected?
Options
- ACommunication plan
- BProject charter
- CAction item
- DProject schedule
How the community answered
(23 responses)- A17% (4)
- B9% (2)
- C4% (1)
- D70% (16)
Explanation
Planning and executing depends upon the documentation of its events. A mishap in such case may adversely affect the budget and time schedule of completing the project.
Topics
#risk management#issue documentation#project schedule#adverse event
Community Discussion