A developer identifies new code that will enhance performance, will not be visible to the user group, and can be done without impact to the timeline. Which of the following steps should the project…
The correct answer is A. Log a change request. A change request is a formal proposal for an alteration to some product or system. Logging a change request enables the project manager to bring significant changes to any project.
Project management concepts
Question
A developer identifies new code that will enhance performance, will not be visible to the user group, and can be done without impact to the timeline. Which of the following steps should the project manager take FIRST?
Options
- ALog a change request.
- BOpen a project issue.
- CAuthorize the new code.
- DAdd the change to the schedule.
How the community answered
(19 responses)- A79% (15)
- B5% (1)
- C11% (2)
- D5% (1)
Explanation
A change request is a formal proposal for an alteration to some product or system. Logging a change request enables the project manager to bring significant changes to any project.