PK0-004 · Question #955

A company is starting a new project. There are a few departments that do not agree with the deliverables and have gone to the steering committee to explain their position. Which of the following…

The correct answer is A. Project sponsor. The project sponsor is the champion of the project.

Project management concepts

Question

A company is starting a new project. There are a few departments that do not agree with the deliverables and have gone to the steering committee to explain their position. Which of the following stakeholders is MOST responsible for defending the project?

Options

  • AProject sponsor
  • BProject manager
  • CProject management office
  • DProject coordinator

How the community answered

(30 responses)
  • A
    87% (26)
  • B
    3% (1)
  • C
    3% (1)
  • D
    7% (2)

Explanation

The project sponsor is the champion of the project.

Topics

#project sponsor#stakeholder roles#steering committee#project governance