Given the following: Which of the following is the critical path?

The correct answer is C. 1, 6, 4, 3, 2, 7. If you draw the critical chain path then C is the only one that forms based on the predecessors with a critical chain of 18.

Tools and documentation

Question

Given the following:

Which of the following is the critical path?

Exhibits

PK0-004 question #941 exhibit 1
PK0-004 question #941 exhibit 2
PK0-004 question #941 exhibit 3

Options

  • A1, 5, 3, 2, 7
  • B1, 6, 5, 3, 2, 7
  • C1, 6, 4, 3, 2, 7
  • D1, 4, 5, 3, 2, 7

How the community answered

(36 responses)
  • A
    8% (3)
  • B
    19% (7)
  • C
    61% (22)
  • D
    11% (4)

Explanation

If you draw the critical chain path then C is the only one that forms based on the predecessors with a critical chain of 18.

Topics

#critical path#network diagram#project scheduling#task dependencies