Given the following: Which of the following is the critical path?
The correct answer is C. 1, 6, 4, 3, 2, 7. If you draw the critical chain path then C is the only one that forms based on the predecessors with a critical chain of 18.
Tools and documentation
Question
Given the following:
Which of the following is the critical path?
Exhibits
Options
- A1, 5, 3, 2, 7
- B1, 6, 5, 3, 2, 7
- C1, 6, 4, 3, 2, 7
- D1, 4, 5, 3, 2, 7
How the community answered
(36 responses)- A8% (3)
- B19% (7)
- C61% (22)
- D11% (4)
Explanation
If you draw the critical chain path then C is the only one that forms based on the predecessors with a critical chain of 18.
Topics
#critical path#network diagram#project scheduling#task dependencies