When a project milestone is completed, which of the following activities ensures the quality of the deliverables at that point in the project?
The correct answer is A. Gate review. A Gate Review is a checkpoint review of project deliverables and performance at the end of each phase or subphase of a project at which point a management review or sign-off may be required. This is also known as a governancegate review.
Project life cycle phases
Question
When a project milestone is completed, which of the following activities ensures the quality of the deliverables at that point in the project?
Options
- AGate review
- BLessons learned
- CAudit
- DBaseline review
How the community answered
(33 responses)- A88% (29)
- B6% (2)
- C3% (1)
- D3% (1)
Explanation
A Gate Review is a checkpoint review of project deliverables and performance at the end of each phase or subphase of a project at which point a management review or sign-off may be required. This is also known as a governancegate review.