Question
A project team identifies the fluctuating cost of a raw material as a risk to the project. Just prior to procuring the material, the price drops substantially. The team decides to double the order of the material and use the surplus in a future project. Which of the following risk strategies does this employ?
Options
- AMitigate
- BExploit
- CAccept
- DTransfer