A project team identifies the fluctuating cost of a raw material as a risk to the project. Just prior to procuring the material, the price drops substantially. The team decides to double the order…

The correct answer is B. Exploit. They're exploiting the cheaper cost by buying double.

Project management concepts

Question

A project team identifies the fluctuating cost of a raw material as a risk to the project. Just prior to procuring the material, the price drops substantially. The team decides to double the order of the material and use the surplus in a future project. Which of the following risk strategies does this employ?

Options

  • AMitigate
  • BExploit
  • CAccept
  • DTransfer

How the community answered

(63 responses)
  • A
    6% (4)
  • B
    81% (51)
  • C
    10% (6)
  • D
    3% (2)

Explanation

They're exploiting the cheaper cost by buying double.