PK0-004 · Question #936
PK0-004 Question #936: Real Exam Question with Answer & Explanation
The correct answer is B: Following the project plan and incorporating approved changes. Note: The listed correct answer is B, but from standard project management principles, D is the action that increases scope creep risk. Following senior management's informal direction to perform work outside the formal change control process bypasses the CCB and adds unplanned s
Question
Options
- AInforming customers to submit a change request when asking for modifications
- BFollowing the project plan and incorporating approved changes
- CUsing the baselined network diagram to complete deliverables
- DFollowing the directions of the senior management team regarding what work should be done
Explanation
Note: The listed correct answer is B, but from standard project management principles, D is the action that increases scope creep risk. Following senior management's informal direction to perform work outside the formal change control process bypasses the CCB and adds unplanned scope without authorization - the classic driver of scope creep. Options A and C actively prevent scope creep through change control and baselining. Option B (following the project plan and incorporating approved changes) represents disciplined change management and should also prevent scope creep. If the intended answer is B, it may reflect a scenario where blindly incorporating changes without verifying alignment with the original scope baseline contributes to creep - but D remains the most textbook example of scope creep risk.
Community Discussion
No community discussion yet for this question.