A project manager receives feedback that a team member is not sharing best practices with the team so they can do their work faster. The project manager sees a bowling trophy at the team member's…
The correct answer is C. Rapport building. The project manager noticed a personal interest (bowling trophy) and used it to initiate an informal one-on-one conversation. This is a classic rapport-building technique - finding common ground with an individual to establish trust and open communication. Rapport building is a…
Question
A project manager receives feedback that a team member is not sharing best practices with the team so they can do their work faster. The project manager sees a bowling trophy at the team member's desk, and invites the team member to go bowling and have a one-on-one conversation. Which of the following describes the project manager's approach?
Options
- APersonal preferences
- BCultural differences
- CRapport building
- DTeam building
How the community answered
(68 responses)- A3% (2)
- B7% (5)
- C88% (60)
- D1% (1)
Explanation
The project manager noticed a personal interest (bowling trophy) and used it to initiate an informal one-on-one conversation. This is a classic rapport-building technique - finding common ground with an individual to establish trust and open communication. Rapport building is a targeted, interpersonal approach focused on connecting with a specific person, distinguishing it from the broader group-focused activity of team building (D). It is not about cultural differences (B) or personal preferences (A), as the PM is strategically leveraging the team member's interest to address a performance concern.