A project manager is asked to provide status reports for the following: - The Chief Executive Officer (CEO), who travels frequently and requires access to ad hoc project status reports - The PMO…

The correct answer is A. Create a real-time dashboard report with filters and post it on the intranet with appropriate. A real-time dashboard with filters and role-based access satisfies all three stakeholder groups from a single source of truth: the CEO can access it on demand from anywhere, the PMO can filter for biweekly/monthly views, and the team can check daily updates. Sending scheduled…

Tools and documentation

Question

A project manager is asked to provide status reports for the following:

  • The Chief Executive Officer (CEO), who travels frequently and

requires access to ad hoc project status reports

  • The PMO, which requires biweekly and monthly project status reports
  • The project team, which requires daily project status reports

Which of the following would be the MOST effective method to satisfy these requests?

Options

  • ACreate a real-time dashboard report with filters and post it on the intranet with appropriate
  • BCreate an email rule to send the status reports at the given intervals.
  • CEmail a weekly, monthly, quarterly, and annual project status report.
  • DUpdate the intranet with daily status reports.
  • ESchedule 2 meeting with the CEO, PMO, and project team to share the pertinent data.

How the community answered

(65 responses)
  • A
    55% (36)
  • B
    23% (15)
  • C
    11% (7)
  • D
    5% (3)
  • E
    6% (4)

Explanation

A real-time dashboard with filters and role-based access satisfies all three stakeholder groups from a single source of truth: the CEO can access it on demand from anywhere, the PMO can filter for biweekly/monthly views, and the team can check daily updates. Sending scheduled emails (B/C) doesn't satisfy the CEO's ad hoc needs and creates report sprawl. Daily intranet updates (D) don't meet the PMO's structured cadences. Scheduling meetings (E) is inefficient for a traveling CEO and doesn't scale.

Topics

#dashboard reporting#communication planning#stakeholder communication#project status reports