Project requirements change regularly, and the development of deliverables follows an iterative approach. Short, regular stand-ups are held to agree on tasks and give updates. Which of the following…

The correct answer is B. Scrum meeting. In the Scrum agile framework, the Daily Scrum (also called the daily stand-up or Scrum meeting) is a short, time-boxed event - typically 15 minutes - held each day for the team to synchronize activities, discuss what was done, what will be done, and any blockers. A war room is…

Project management concepts

Question

Project requirements change regularly, and the development of deliverables follows an iterative approach. Short, regular stand-ups are held to agree on tasks and give updates. Which of the following is the name given to these daily stand-ups?

Options

  • AWar room
  • BScrum meeting
  • CBrainstorming session
  • DProject status review

How the community answered

(28 responses)
  • B
    89% (25)
  • C
    4% (1)
  • D
    7% (2)

Explanation

In the Scrum agile framework, the Daily Scrum (also called the daily stand-up or Scrum meeting) is a short, time-boxed event - typically 15 minutes - held each day for the team to synchronize activities, discuss what was done, what will be done, and any blockers. A war room is a physical or virtual collaboration space, brainstorming sessions generate ideas, and a project status review is a formal periodic meeting - none of these describe daily iterative stand-ups.