nerdexam
CompTIA

PK0-004 · Question #75

Which of the following is a schedule that illustrates the duration of an activity?

The correct answer is C. Gantt chart. A Gantt chart is a bar chart that plots project activities along a timeline, visually representing both the start and end dates and the duration of each activity.

Tools and documentation

Question

Which of the following is a schedule that illustrates the duration of an activity?

Options

  • AProcess diagram
  • BIshikawa diagram
  • CGantt chart
  • DPareto chart

How the community answered

(24 responses)
  • B
    4% (1)
  • C
    92% (22)
  • D
    4% (1)

Why each option

A Gantt chart is a bar chart that plots project activities along a timeline, visually representing both the start and end dates and the duration of each activity.

AProcess diagram

A process diagram illustrates the sequence and flow of steps in a process, not the duration or timeline of project activities.

BIshikawa diagram

An Ishikawa (fishbone) diagram is a cause-and-effect tool used in quality management to identify root causes of a problem, not to schedule activities.

CGantt chartCorrect

A Gantt chart maps each scheduled activity as a horizontal bar whose length corresponds to its duration, against a calendar timeline. This makes it the standard tool for communicating schedule information, showing activity durations, dependencies, and overall project timeline at a glance.

DPareto chart

A Pareto chart ranks defects or issues by frequency to identify the vital few causes responsible for most problems, and is not a scheduling tool.

Concept tested: Gantt chart as a project schedule visualization tool

Topics

#Gantt chart#activity duration#schedule visualization#scheduling tools

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice