PK0-004 · Question #76
A customer has requested additional features for an active project. Which of the following steps should take place NEXT?
The correct answer is B. Evaluate the impact of the changes. The elements of a change management process include identifying and documenting the change (using templates and a change log), evaluating the impact, obtaining approval from the CCB, implementing the change, validating the change, updating the project management plan documents…
Question
A customer has requested additional features for an active project. Which of the following steps should take place NEXT?
Options
- AImplement the requested changes.
- BEvaluate the impact of the changes.
- CUpdate all project documents.
- DSubmit the requested changes to the CCB
How the community answered
(22 responses)- A9% (2)
- B82% (18)
- C5% (1)
- D5% (1)
Explanation
The elements of a change management process include identifying and documenting the change (using templates and a change log), evaluating the impact, obtaining approval from the CCB, implementing the change, validating the change, updating the project management plan documents, and communicating as needed. Answer is first evaluate and then send to CCB for a
Topics
Community Discussion
No community discussion yet for this question.