PK0-004 · Question #76
PK0-004 Question #76: Real Exam Question with Answer & Explanation
The correct answer is B: Evaluate the impact of the changes.. The elements of a change management process include identifying and documenting the change (using templates and a change log), evaluating the impact, obtaining approval from the CCB, implementing the change, validating the change, updating the project management plan documents, a
Question
Options
- AImplement the requested changes.
- BEvaluate the impact of the changes.
- CUpdate all project documents.
- DSubmit the requested changes to the CCB
Explanation
The elements of a change management process include identifying and documenting the change (using templates and a change log), evaluating the impact, obtaining approval from the CCB, implementing the change, validating the change, updating the project management plan documents, and communicating as needed. Answer is first evaluate and then send to CCB for a
Community Discussion
No community discussion yet for this question.