PK0-004 · Question #739

PK0-004 Question #739: Real Exam Question with Answer & Explanation

The correct answer is C: Host a kickoff meeting.. After the project team is identified, the standard next step in project management is to host a kickoff meeting to formally align the team on goals and expectations.

Question

A project has been created, and the project team has been identified. Which of the following is the NEXT step?

Options

  • ARelease an article on the company blog.
  • BConduct a company town hall.
  • CHost a kickoff meeting.
  • DPost a notice on social media.

Explanation

After the project team is identified, the standard next step in project management is to host a kickoff meeting to formally align the team on goals and expectations.

Common mistakes.

  • A. Publishing a company blog article is a marketing or communications activity and is not a standard project management step in the project lifecycle.
  • B. A company town hall is a broad organizational communication event and is not the appropriate project-level next step after team identification.
  • D. Posting on social media is an external communications activity unrelated to formal project initiation processes.

Concept tested. Project kickoff meeting as standard initiation step

Reference. https://www.pmi.org/learning/library/project-kickoff-meeting-importance-6630