CompTIA
PK0-004 · Question #740
PK0-004 Question #740: Real Exam Question with Answer & Explanation
The correct answer is D: Project sponsors. When a department's lack of cooperation blocks project progress, the project sponsor is the correct escalation point because they hold the organizational authority to compel resolution.
Question
A project manager is not receiving cooperation from a department that is vital to the success of a project. Because of this, the project cannot move forward. Which of the following is the BEST place the project manager should go to get help with this issue?
Options
- AProject management office
- BProject stakeholders
- CProject team
- DProject sponsors
Explanation
When a department's lack of cooperation blocks project progress, the project sponsor is the correct escalation point because they hold the organizational authority to compel resolution.
Common mistakes.
- A. The PMO provides standards and support but typically does not hold the authority to compel cooperation from an unresponsive department.
- B. Project stakeholders may lack the authority to direct other departments and could themselves be part of the non-cooperating group.
- C. The project team has no organizational authority over departments outside their own and cannot compel cross-departmental cooperation.
Concept tested. Project sponsor authority to resolve escalated roadblocks
Reference. https://www.pmi.org/learning/library/role-executive-sponsor-project-success-9985
Community Discussion
No community discussion yet for this question.