PK0-004 · Question #735
A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project…
The correct answer is B. Issue log. When a risk event actually occurs and becomes an active problem, it transitions from the risk register to the issue log, which must be updated first.
Question
A project manager identified a risk in a geographically unstable area. During the project, a volcano erupts, preventing project team access. Which of the following documents should the project manager update FIRST?
Options
- AProject schedule
- BIssue log
- CRisk register
- DScope statement
How the community answered
(29 responses)- A3% (1)
- B79% (23)
- C10% (3)
- D7% (2)
Why each option
When a risk event actually occurs and becomes an active problem, it transitions from the risk register to the issue log, which must be updated first.
The project schedule is updated after the issue is logged and its impact on timeline is assessed, not as the immediate first step.
Once a risk materializes into an actual event, it is no longer a potential risk but an active issue requiring immediate tracking and resolution. The issue log is the designated document for capturing active problems that are currently impacting the project. Updating the issue log first ensures the problem is formally recorded, assigned, and managed before any secondary updates to schedule or other documents.
The risk register was already updated when the risk was first identified - once the event occurs, it becomes an active issue, not a pending risk.
The scope statement defines project boundaries and deliverables and is not used to track active operational problems.
Concept tested: Issue log vs risk register when a risk materializes
Source: https://www.pmi.org/learning/library/risk-register-issue-log-differences-6626
Topics
Community Discussion
No community discussion yet for this question.