As part of a project, employee production cannot proceed unless certain thresholds of the product are achieved. Which of the following is this called?
The correct answer is D. Quality gate. If it has to meet a certain threshold then it's quality gate.
Project management concepts
Question
As part of a project, employee production cannot proceed unless certain thresholds of the product are achieved. Which of the following is this called?
Options
- ACritical path
- BMilestone
- CPhase gate
- DQuality gate
- EToll gate
How the community answered
(33 responses)- A3% (1)
- C3% (1)
- D94% (31)
Explanation
If it has to meet a certain threshold then it's quality gate.
Topics
#quality gate#project thresholds#quality management#control points