As part of a project, employee production cannot proceed unless certain thresholds of the product are achieved. Which of the following is this called?

The correct answer is D. Quality gate. If it has to meet a certain threshold then it's quality gate.

Project management concepts

Question

As part of a project, employee production cannot proceed unless certain thresholds of the product are achieved. Which of the following is this called?

Options

  • ACritical path
  • BMilestone
  • CPhase gate
  • DQuality gate
  • EToll gate

How the community answered

(33 responses)
  • A
    3% (1)
  • C
    3% (1)
  • D
    94% (31)

Explanation

If it has to meet a certain threshold then it's quality gate.

Topics

#quality gate#project thresholds#quality management#control points