A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?
The correct answer is C. LOI. https://en.wikipedia.org/wiki/Letter_of_intent
Tools and documentation
Question
A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?
Options
- ASLA
- BSOW
- CLOI
- DRFQ
How the community answered
(29 responses)- A3% (1)
- B3% (1)
- C86% (25)
- D7% (2)
Explanation
Topics
#LOI#procurement process#vendor management#contract documents