A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?

The correct answer is C. LOI. https://en.wikipedia.org/wiki/Letter_of_intent

Tools and documentation

Question

A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?

Options

  • ASLA
  • BSOW
  • CLOI
  • DRFQ

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    86% (25)
  • D
    7% (2)

Explanation

https://en.wikipedia.org/wiki/Letter_of_intent

Topics

#LOI#procurement process#vendor management#contract documents